Taking a contract dispute all the way

Scope
  • As part of a long-term regulatory monitoring contract with a customer, we identified that a utility was planning to terminate selected special contracts early
  • We disputed the termination on our client’s behalf
  • We organized a new coalition of industrial customers and legal counsel to file a complaint with the Public Utility Commission (PUC)
  • After many months, the PUC denied the claim
  • We took the case to the State Supreme Court
Results

The case was won at the State Supreme Court level

Customer Value

Our customer saved more than $1 million